Question: You have prepared the following schedule for a project in which the key resources is a tractor. There are three tractors available to the project.

You have prepared the following schedule for a project in which the key resources is a tractor. There are three tractors available to the project. Activities A and D require one tractor to complete while activities B, C, E and F require 2 tractors.
Develop a resource-constrained schedule in the loading chart that follows. Use the parallel method and heuristics given. Be sure to update each period as the computer would do. Record the early start (ES), late finish (LF) and slack (SL) for the newschedule.
You have prepared the following schedule for a project in

Legend ESI ID | EF SL LS DURNL 6 4 10 SL 5 D 10 10 F 12 10 212 Resource 0 20 0 55 Minimum slack Smallest duration Lowest identification number 73 10 D RES DUR ES LF SL 0 1 2 3 4 5 6 7B 9 10 11 13 14 15 C 2 4 D 15 F 2 2 Resources available 3 3 3 3 33 3 3 3 3 3 3 3 33

Step by Step Solution

3.43 Rating (175 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Log of Parallel Method of Scheduling PERIOD ACTIVITY CHANGES 01 B Schedule Activity B first by minim... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

177-B-M-L-P-M (1394).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!