Question: there is another option that says : 24. Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B,C A D 38 50 62 E

there is another option that says : 24. Time

there is another option that says : 24.

Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B,C A D 38 50 62 E 90 99 108 End 85 100 115 F 25 31 End 91 100 115 F End 62 65 68 B D 19 E What is the estimated standard deviation in the time for activity E? Multiple Choice 16 days 3 days 4 days 2 days C