Question: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B,C A D 38 50 62 B E 90 99 108 End 85 100 115

Time Estimates (days) Activity PrecedesTime Estimates (days) Activity Precedes

Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B,C A D 38 50 62 B E 90 99 108 End 85 100 115 D F F 19 25 31 E End 91 100 115 F End 62 65 68 Draw a precedence diagram. What path of activities would you focus your project management efforts on and why? What is the probability that this project will be completed within 205 days? (show all work for full credit)