Question: This approach for constructing a WBS involves starting with top hierarchy tasks of the project and breaking those tasks into their lowest level of subordinate

This approach for constructing a WBS involves starting with top hierarchy tasks of the project and breaking those tasks into their lowest level of subordinate tasks.
a. analogy
b. bottom-up
c. top-down
d. mind mapping