Question: This Assignment is worth 20 Marks. ANSWER ALL QUESTIONS. Please ensure you use the cover page. Please use the following information and create a Pert
This Assignment is worth 20 Marks. ANSWER ALL QUESTIONS. Please ensure you use the cover page.
Please use the following information and create a Pert and a Gantt Chart.
| Activity | Predecessor (Pr) | Optimistic (0) | Most Likely (ML) | Pessimistic (P) | Duration (D) |
| Durations in Months |
| ||||
| A |
| 4 | 5 | 7 |
|
| B |
| 7 | 8 | 12 |
|
| C |
| 8 | 10 | 13 |
|
| D | B | 10 | 11 | 13 |
|
| E | C | 0.5 | 1 | 11 |
|
| F | D | 2 | 5 | 8 |
|
| G | A, B | 9 | 10 | 12 |
|
| H | E | 3 | 7 | 16 |
|
| I | G | 2 | 1 | 14 |
|
| J | F, G | 10 | 5 | 13 |
|
- What are the Critical and Slack times you have identified?
- A fence 10 feet by ten feet is being built for $40,000.00 in 4 weeks. During week 2 , 15 feet has been completed. Calculate the following:
- Estimate to Completion (ETC)
- Variance at Completion (VAC)
- To Complete Performance Index (TCPI)