Question: This Assignment is worth 20 Marks. ANSWER ALL QUESTIONS. Please ensure you use the cover page. Please use the following information and create a Pert

This Assignment is worth 20 Marks. ANSWER ALL QUESTIONS. Please ensure you use the cover page.

Please use the following information and create a Pert and a Gantt Chart.

Activity

Predecessor

(Pr)

Optimistic

(0)

Most Likely

(ML)

Pessimistic

(P)

Duration

(D)

Durations in Months

A

4

5

7

B

7

8

12

C

8

10

13

D

B

10

11

13

E

C

0.5

1

11

F

D

2

5

8

G

A, B

9

10

12

H

E

3

7

16

I

G

2

1

14

J

F, G

10

5

13

  1. What are the Critical and Slack times you have identified?
  2. A fence 10 feet by ten feet is being built for $40,000.00 in 4 weeks. During week 2 , 15 feet has been completed. Calculate the following:
  • Estimate to Completion (ETC)
  • Variance at Completion (VAC)
  • To Complete Performance Index (TCPI)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!