Question: This is a Project Network for opening a new restaurant in a 120 day period of time. The project duration has been reduced by 15%.

This is a Project Network for opening a new

This is a Project Network for opening a new restaurant in a 120 day period of time.

The project duration has been reduced by 15%.

What does this mean for your project (number of time units) and indicate how do you intend to do reduce your project network.

Project Network o Critical Path identified (orange) 62 14 76 76 3 79 K 61 110 kick-off party 797 86 O A 14 14 B 19 19 E 49 49 103 7 110 construction Security 61 66 86 5 91 103 110 R 111 online ordering Host kick-off party 101 S 12 Open doors 111 1 112 Interview'Hire 91 96 96 103 110 1 111 14 63 68 Uniform & Dress code 103 Q 106 14 C 74 915 96 AUT Final Inspectione completed 47 60 107 107 3 110 Legend ES ID EF SL Description LS DUR LF

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!