Question: This is a schedule for a short school project. Use the values in the table to answer the questions below: Activity Predecessor Optimistic Likely Pessimistic
This is a schedule for a short school project. Use the values in the table to answer the questions below:
| Activity | Predecessor | Optimistic | Likely | Pessimistic |
| A | -- | 1 | 8 | 9 |
| B | A | 4 | 5 | 12 |
| C | A | 10 | 12 | 20 |
| D | B | 5 | 12 | 13 |
| E | C, D | 1 | 3 | 5 |
The variance for activity C is:
a.
1.78
b.
None of the above
c.
1.74
d.
2.78
e.
3.78
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
