Question: This is a schedule for a short school project. Use the values in the table to answer the questions below: Activity Predecessor Optimistic Likely Pessimistic

This is a schedule for a short school project. Use the values in the table to answer the questions below:

Activity

Predecessor

Optimistic

Likely

Pessimistic

A

--

1

8

9

B

A

4

5

12

C

A

10

12

20

D

B

5

12

13

E

C, D

1

3

5

The total float for the above project is:

a.

None of the above

b.

13

c.

zero

d.

4

e.

7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!