Question: this is all the information given and should be enough Given the following production schedule, compute the available-to-promise quantities. Week 1 2 3 4 5

this is all the information given and should be
this is all the information given and should be
this is all the information given and should be enough
Given the following production schedule, compute the available-to-promise quantities. Week 1 2 3 4 5 6 7 8 MPS BI=20 20 0 20 20 0 20 20 20 Cust. Orders 10 10 10 10 10 0 0 10 ATP Qla Homework Unanswered What is the discrete ATP in period 8? Type your numeric answer and submit Qib Homework . Unanswered What is the cumulative ATP in period 8? Type your numeric answer and submit