Question: This is the model that describes stakeholders based off assessments of their levels of authority, urgency, and legitimacy: Stakeholder priority Salience model Stakeholder model Saltine

This is the model that describes stakeholders based off assessments of their levels of authority, urgency, and legitimacy:

Stakeholder priority

Salience model

Stakeholder model

Saltine model

Stakeholder cube

When is the best time to start the process of stakeholder identification engagement?

after completing risk analysis

after completing a RACI analysis

as soon as you have a business plan

as soon as you have approved the project charter

any time within the project is fine