Question: This is the question 4 it is based on.. Based on your work breakdown structure on question 4, sequence the activities by developing a precedence

This is the question 4 it is based on.. Based on

This is the question 4 it is based on.. Based on

This is the question 4 it is based on.. Based on

This is the question 4 it is based on..

Based on your work breakdown structure on question 4, sequence the activities by developing a precedence table. Use the table provided below to complete your answer. 3.1 Sequence the activities of the work packages to show the order in which they are performed. 3.2 In doing that, determine the relationship between the activities, clearly identifying which activities should be done first, which are next (in series) as well as which activities can be performed at the same time (in parallel) to save time. NB: have a minimum of 5 activities. Plot your answer to 3.2 on the precedence diagram method (PDM)table below. Question 4 (20 marks) 4.1 Based on the diagram above calculate the duration of the project (in weeks). Include both the forward pass and backward pass calculations. (16) 4.2 Identify the critical path for this project. (4) Question 4 (20 marks) 4.1 Based on the diagram above calculate the duration of the project (in weeks). Include both the forward pass and backward pass calculations. (16) 4.2 Identify the critical path for this project. (4)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!