Question: In a PERT network, non - critical activities that have little slack need to be monitored closely: because they are causing the entire project to
In a PERT network, noncritical activities that have little slack need to be monitored closely:
because they are causing the entire project to be delayed.
because slack is undesirable and needs to be eliminated.
because nearcritical paths could become critical paths with small delays in these activities.
because PERT treats all activities as equally important.
because they have a high risk of not being completed.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
