Question: In a PERT network, non - critical activities that have little slack need to be monitored closely: because they are causing the entire project to

In a PERT network, non-critical activities that have little slack need to be monitored closely:
because they are causing the entire project to be delayed.
because slack is undesirable and needs to be eliminated.
because near-critical paths could become critical paths with small delays in these activities.
because PERT treats all activities as equally important.
because they have a high risk of not being completed.