Question: This table represents the actual cost ( AC ) of Dalron Construction project. Week 1 2 3 4 5 6 7 Task 1 5 2
This table represents the actual cost AC of Dalron Construction project.
Week
Task
Task
Task
Total
Cumulative
What is the actual cost AC at the end of week
Answer:
Question
Not yet answered
Marked out of
Flag question
Question text
At the end of week the work was completed as follows:
Task is completed,
Task is completed and
Task is completed.
What is the total earned value EV at the end of week
Answer:
Question
Not yet answered
Marked out of
Flag question
Question text
What is the CV Cost Variance at the end of week
Answer:
Question
Not yet answered
Marked out of
Flag question
Question text
What is the SV Schedule Variance at the end of week
Answer:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!