Question: This table represents the actual cost ( AC ) of Dalron Construction project. Week 1 2 3 4 5 6 7 Task 1 5 2

This table represents the actual cost (AC) of Dalron Construction project.
Week
1234567
Task 152520
Task 251520
15
1512
Task 35101515
Total
Cumulative
What is the actual cost (AC) at the end of week 7?
Answer:
177
Question 78
Not yet answered
Marked out of 1.0
Flag question
Question text
At the end of week 7 the work was completed as follows:
Task 1 is 100% completed,
Task 2 is 80% completed and
Task 3 is 60% completed.
What is the total earned value (EV) at the end of week 7?
Answer:
Question 79
Not yet answered
Marked out of 1.0
Flag question
Question text
What is the CV [Cost Variance] at the end of week 7?
Answer:
Question 80
Not yet answered
Marked out of 1.0
Flag question
Question text
What is the SV [Schedule Variance] at the end of week 7?
Answer:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!