Question: Below is the Planned time - phased value ( PV ) of Dalron Construction project. Week 1 2 3 4 5 6 7 8 9

Below is the Planned time-phased value (PV) of Dalron Construction project.
Week
12345678910
Task 152520
Task 2510151515121082
Task 35101515753
Total
Cumulative
What is the total budgeted cost at completion (BAC) of Dalron Construction project?
Answer: