Question: Below is the Planned time - phased value ( PV ) of Dalron Construction project. Week 1 2 3 4 5 6 7 8 9
Below is the Planned timephased value PV of Dalron Construction project.
Week
Task
Task
Task
Total
Cumulative
What is the total budgeted cost at completion BAC of Dalron Construction project?
Answer:
Question
Not yet answered
Marked out of
Flag question
Question text
What is the budgeted cost at completion BAC of Task
Answer: