Question: This table will cover information for Q7-Q8 year CF project A CF project B 0 -1000 -800 1 600 300 2 700 300 3 300
This table will cover information for Q7-Q8
year CF project A CF project B
0 -1000 -800
1 600 300
2 700 300
3 300
4 400
With discount rate 7%
what is project B's NPV?
what is annualized EAC (annualized NPV) for project A?