Question: This week, the team will make a Burn-Down Chart using MS Excel given the following: Your vacation planning project has a total of 24 tasks.
This week, the team will make a Burn-Down Chart using MS Excel given the following:
- Your vacation planning project has a total of 24 tasks.
- Each task requires 8 hours to complete.
- You have completed the first six tasks, with the following results:
- Task 1 required 6 hours to complete.
- Task 2 took 8 hours to complete.
- Task 3 took 7 hours to complete.
- Task 4 took 9 hours to complete.
- Task 5 took 4 hours to complete.
- Task 6 took 8 hours to complete.
- Each of the completed tasks required a single day each to complete.
As a Team
- make a Burn-Down Chart.
- Represent the estimated remaining hours as a dashed red line.
- Represent the actual remaining hours as a solid blue line.
- Define areas above the line and below.