Question: Three Time Estimates Activity Optimistic Time Most Likely Time Pessimistic Time A: Concept Development 3 12 24 Plan Definition B: Define Project scope 1 2

Three Time Estimates

Activity Optimistic Time Most Likely Time Pessimistic Time
A: Concept Development 3 12 24
Plan Definition
B: Define Project scope 1 2 12
C: Develop broad schedule 0.25 0.5 1
D: Detailed cost estimates 0.2 0.3 0.5
E: Develop staffing plan 0.2 0.3 0.6
Design and Construction
F: Detailed engineering 2 3 6
G: Facility construction 8 12 24
H: Mobilitization of employees 0.5 2 4
I: Procurement of equipment 1 3 12
Start Up and Turnover
J: Pre-Start- up inspection 0.25 0.5 1
K: Recruiting and training 0.25 0.5 1
L: Solving start-up problems 0 1 2
M: Centerlining 0 1 4

Three Cost Rate Estimates:

Activity Optimistic Time Most Likely Time Pessimistic Time
A: Concept Development 1,900 2,000 2,300
Plan Definition
B: Define Project scope 23,750 25,000 28,750
C: Develop broad schedule 15,200 16,000 18,400
D: Detailed cost estimates 28,500 30,000 34,500
E: Develop staffing plan 27,000 30,000 33,000
Design and Construction
F: Detailed engineering 360,000 400,000 440,000
G: Facility construction 112,500 125,000 156,250
H: Mobilitization of employees 270,000 300,000 330,000
I: Procurement of equipment 360,000 400,000 440,000
Start Up and Turnover
J: Pre-Start- up inspection 90,000 100,000 110,000
K: Recruiting and training 540,000 600,000 660,000
L: Solving start-up problems 90,000 100,000 110,000
M: Centerlining 45,000 50,000 55,000

Develop Histograms for both the project completion time and the cost to complete the project. What do these histograms tell you?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!