Question: Three Time Estimates Activity Optimistic Time Most Likely Time Pessimistic Time A: Concept Development 3 12 24 Plan Definition B: Define Project scope 1 2
Three Time Estimates
| Activity | Optimistic Time | Most Likely Time | Pessimistic Time |
| A: Concept Development | 3 | 12 | 24 |
| Plan Definition | |||
| B: Define Project scope | 1 | 2 | 12 |
| C: Develop broad schedule | 0.25 | 0.5 | 1 |
| D: Detailed cost estimates | 0.2 | 0.3 | 0.5 |
| E: Develop staffing plan | 0.2 | 0.3 | 0.6 |
| Design and Construction | |||
| F: Detailed engineering | 2 | 3 | 6 |
| G: Facility construction | 8 | 12 | 24 |
| H: Mobilitization of employees | 0.5 | 2 | 4 |
| I: Procurement of equipment | 1 | 3 | 12 |
| Start Up and Turnover | |||
| J: Pre-Start- up inspection | 0.25 | 0.5 | 1 |
| K: Recruiting and training | 0.25 | 0.5 | 1 |
| L: Solving start-up problems | 0 | 1 | 2 |
| M: Centerlining | 0 | 1 | 4 |
Three Cost Rate Estimates:
| Activity | Optimistic Time | Most Likely Time | Pessimistic Time |
| A: Concept Development | 1,900 | 2,000 | 2,300 |
| Plan Definition | |||
| B: Define Project scope | 23,750 | 25,000 | 28,750 |
| C: Develop broad schedule | 15,200 | 16,000 | 18,400 |
| D: Detailed cost estimates | 28,500 | 30,000 | 34,500 |
| E: Develop staffing plan | 27,000 | 30,000 | 33,000 |
| Design and Construction | |||
| F: Detailed engineering | 360,000 | 400,000 | 440,000 |
| G: Facility construction | 112,500 | 125,000 | 156,250 |
| H: Mobilitization of employees | 270,000 | 300,000 | 330,000 |
| I: Procurement of equipment | 360,000 | 400,000 | 440,000 |
| Start Up and Turnover | |||
| J: Pre-Start- up inspection | 90,000 | 100,000 | 110,000 |
| K: Recruiting and training | 540,000 | 600,000 | 660,000 |
| L: Solving start-up problems | 90,000 | 100,000 | 110,000 |
| M: Centerlining | 45,000 | 50,000 | 55,000 |
Calculate the probability that the project can be completed within 30 months. What is the probability that the project will take longer than 40 months? What is the probability that the project will take between 30-40 months? What is the probability the project will cost 5.1 million or less to complete? The probability the project will cost between 5 and 6 million to complete?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts