Question: Time Estimates ( days ) Activity Optimistic Most Likely Pessimistic Immediate Predecessor ( s ) A 5 7 8 - B 5 8 1 1

Time Estimates (days)
Activity Optimistic Most Likely Pessimistic Immediate Predecessor(s)
A 578-
B 5811-
C 345-
D 111626 A
E 71011 B
F 246 C, E
G 3810 D
H 578 F
I 71117 G, H
J 444 G