Question: TIME ESTIMATES (IN WEEKS) IMMEDIATE MOST ACTIVITY PREDECESSOR(S) OPTIMISTIC LIKELY PESSIMISTIC A 4 8 10 B A 2 8 24 C A 00 12 16

TIME ESTIMATES (IN WEEKS) IMMEDIATE MOST ACTIVITY

TIME ESTIMATES (IN WEEKS) IMMEDIATE MOST ACTIVITY PREDECESSOR(S) OPTIMISTIC LIKELY PESSIMISTIC A 4 8 10 B A 2 8 24 C A 00 12 16 D A 4 6 10 E B 1 2 3 F E, C 6 20 w 00 G E, C 2 4 H F 2 2 2 1 F 6 6 6 J D, G, H 4 6 12 K 1,J 2 N 3 a) Make the network diagram. b) Calculate the expected time and variance for each activity. c) Construct the PERT diagram. d) Calculate the value for Critical Path. e) Compute the Project Variance and Project Standard Deviation