Question: What is the expected duration for Activity B What is the Expected duration for this PERT schedule?' What is the critical path of this PERT

What is the expected duration for Activity B

What is the Expected duration for this PERT schedule?'

What is the critical path of this PERT schedule?

What is the Early Start, Early Finish for Activity D?

What is the variance for Activity G?

What is the Late Start, Late Finish for Activity F?
What is the probability that the project can be completed in 26 days?
What is the probability that the project can be completed in 22 days?
What is the total variance for the critical path?

Use the following table of activities and their respective optimistic, most likely, and pessimistic activity durations the these questions. Be sure to carry two decimal places for activity durations.

Activity Predecessor optimistic most likely pessimistic
A - 6 8 10
B A 1 2 3
C - 6 9 12
D B 2 5 11
E C 5 8 11
F C 2 4 8
G D,E 6 7 10
H E,F 4 6 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!