Question: What is the expected duration for Activity B What is the Expected duration for this PERT schedule?' What is the critical path of this PERT
What is the expected duration for Activity B
What is the Expected duration for this PERT schedule?'
| What is the critical path of this PERT schedule? |
What is the Early Start, Early Finish for Activity D?
What is the variance for Activity G?
| What is the Late Start, Late Finish for Activity F? |
| What is the probability that the project can be completed in 26 days? |
| What is the probability that the project can be completed in 22 days? |
| What is the total variance for the critical path? |
Use the following table of activities and their respective optimistic, most likely, and pessimistic activity durations the these questions. Be sure to carry two decimal places for activity durations.
| Activity | Predecessor | optimistic | most likely | pessimistic |
| A | - | 6 | 8 | 10 |
| B | A | 1 | 2 | 3 |
| C | - | 6 | 9 | 12 |
| D | B | 2 | 5 | 11 |
| E | C | 5 | 8 | 11 |
| F | C | 2 | 4 | 8 |
| G | D,E | 6 | 7 | 10 |
| H | E,F | 4 | 6 | 8 |