Question: Time left 0 : 2 8 : 4 4 The above Gantt chart shows a project with three tasks and it needs 5 weeks to
Time left ::
The above Gantt chart shows a project with three tasks and it needs weeks to finish. The project deadline should be after two
weeks from the project starting time The normal cost as planned for task is task is and task is
There is a penalty of per week for every week delay after two weeks. The project manager can crash the durations of task
and task by allocating more resources. After crashing tasks and the total cost of Task and Task will be as follows:
Task and Task for one week crashing,
Task and Task for two weeks crashing.
Task and Task for three weeks crashing.
The project manager has the following scenarios to do:
Scenario : Leave the project without crashing.
Scenario : Crash task and task for one week.
Scenario : Crash task and task for two weeks.
Scenario : Crash task and task for three weeks.
The project total cost of scenario is
The project total cost of scenario is
The project total cost of scenario is
The project total cost of scenario is
The project manager will choose:
with cost saving is
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock