Question: Time left 0:58:36 A simple CPM network has five activities, A, B, C, D, and E.A is an immediate predecessor of C and of D.

 Time left 0:58:36 A simple CPM network has five activities, A,

Time left 0:58:36 A simple CPM network has five activities, A, B, C, D, and E.A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. O a. There are 10 paths in this network. O b. There are five paths in this network. There are four paths in this network O d. There are two paths in this network. O e. There are six paths in this network. OC