Question: Time left 1 : 1 6 : 5 7 LS = L F - DUR Backward calculation SI = LFEF or LS - ES Draw

Time left 1:16:57
LS =LF- DUR Backward calculation
SI = LFEF or LS-ES
Draw the network diagram on paper or open this file and save it on your computer as 'Q47_Your Name').
Calculate the ES, EF.
Show your work on your diagram (later you will be asked to upload the work on Moodle).
Answer the question below: what is the project total duration?