Question: Time Remaining 1 2 3 points The expected duration of a path is equal to the sum of the expected times of the activities on
Time Remaining
points
The expected duration of a path is equal to
the sum of the expected times of the activities on that path
the average of the minimum time, maximum time, and most likely time
the sum of the pessimistic times of the activities on that path, minus the sum of the optimistic times of the activities on that path the square root of the variances of the activities on that path