Question: Time (Weeks) Normal Crash Normal Crash Immediate Time Time Cost Cost Crash Cost per Activity Predecessor (NT) (CT) (NC) (CC) NT-CT CC-NC WEEK A

Time (Weeks) Normal Crash Normal Crash Immediate Time Time Cost Cost Crash

Time (Weeks) Normal Crash Normal Crash Immediate Time Time Cost Cost Crash Cost per Activity Predecessor (NT) (CT) (NC) (CC) NT-CT CC-NC WEEK A 3 2 $300 $400 1 $100 $100 B - 10 9 $300 $700 1 $400 $400 C A 4 2 $500 $600 2 $100 $50 D B, C 5 3 $150 $225 1 $75 $75 E D 2 1 $450 $475 1 $25 $25 F B 6 2 $200 $800 4 $600 $150 A (3) C (4) D (5) E (2) B (10) F (6)