Question: Time X Scope Cost X X * Cliff Gray, Erik Larson, & Pinyarat Sirisomboonsuk, doctoral candidate at Rawls College of Business, Texas Tech University. Constrain

Time
X
Scope Cost
X
X
* Cliff Gray, Erik Larson, & Pinyarat Sirisomboonsuk, doctoral candidate at Rawls College of Business, Texas Tech University.
Constrain Enhance Accept
616
Appendix 2 Computer Project Exercises 617 Connor Gage, the project manager, has formed his project team and the members
have come up with the following work breakdown structure.
1.0 POM+Project
1.1 R&D product development
1.1.1 Need survey 1.1.2 Set product specs 1.1.3 Shelf life report 1.1.4 Nutrition report
1.2 Secure fruit suppliers
1.3 Initial Production
1.3.1 Equipment rehab 1.3.2 Production trials 1.3.3 Quality trials 1.3.4 Quality metrics 1.3.5 Quality training
1.4 Distribution
1.4.1 Market testing 1.4.2 Package design 1.4.3 Select distributors
1.5 Legal
1.5.1 Complete FDA certification 1.5.2 Register trademark
1.6 Prepare product launch
Part 1
1. Develop the WBS outline using the software available (save your file).
2. Use this file and the information provided below to create a project schedule.
3. The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.
4. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given off.
5. The project team works eight-hour days, Monday through Friday.
6. The project will begin on January 3,2012.
7. Based on this schedule, submit a memo that answers the following questions:
a. When is the project estimated to be completed? How many working days will it take?
b. What is the critical path?
c. Which activity has the most total slack?
d. How sensitive is this network?
e. Identify two sensible milestones and explain your choice.
618 Appendix 2
Computer Project Exercises
Include the following (one page) printouts:
A Gantt chart.
A network diagram highlighting the critical path.
A schedule table reporting ES, LS, EF, LF, and slack for each activity.
Hints: Change the timescale to months and weeks. The estimated duration of the project is 135 days.
Remember: Save your files for future exercises!
The following information has been derived from the WBS. Note that the activity number is what appears in the software with the complete WBS entered.
#* Activity Duration
Predecessor(s)
None 3
4
45,647,9
101112
5,615
5,67,157,15
13,16,17,19FS +25 days, 20FS +15 days
3 Need survey
4 Set product specs
5 Shelf life report
6 Nutrition report
7 Select fruit suppliers
9 Equipment rehab
10 Production trials
11 Quality trials
12 Quality metrics
13 Quality training
15 Market testing
16 Package design
17 Select distributors
19 Complete FDA certification
20 Register trademark
21 Prepare product launch
FS = Finish to Start lag
Part 2
201510
5
20
30
15
20
5
15
30
15
25
15
5
15
Remember the old saying, A project plan is not a schedule until resources are com- mitted. This exercise illustrates this sometime subtle, but important point.
Using your files from Part 1, input resources and their costs if you have not already done so. All information is found in Tables A2.1 and A2.2.
Prepare a memo that addresses the following questions:
1. Which if any of the resources are overallocated?
2. Assume that the project is time constrained and try to resolve any overallocation
problems by leveling within slack. What happens?
3. What is the impact of leveling within slack on the sensitivity of the network?
Include a Gantt chart with the schedule table after leveling within slack.
4. Assume the project is resource constrained and resolve any overallocation problems by leveling outside of slack. What happens?
TABLE A2.1
Resource Assignments
TABLE A2.2
Resources Availability and Pay Rates
Appendix 2
Computer Project Exercises 619
Activity
Need survey
Set product specs
Shelf life report
Nutrition report
Select fruit suppliers Equipment rehab Production trials
Quality trials
Quality metrics
Quality training
Market testing
Package design
Select distributors Complete FDA certification Register trademark Prepare product launch
Resources
MRKT (500%)
R&D (400%), MRKT (200%)
R&D (300%)
R&D (300%)
PURCH (100%)
ENG (1,000%), PROD (2,000%)
PROD (1,500%), PURCH (100%), ENG (1,000%) QUAL (300%), PROD (500%)
QUAL (300%), PROD (100%)
QUAL (300%), PROD (1,500%)
MRKT (500%)
DESIGN (300%), MRKT (100%)
MRKT (500%)
LEGAL (300%)
LEGAL (300%)
QUAL (300%), PURCH (200%), PROD (1,500%), MRKT (500%), ENG (500%), R&D (100%)
Resource
Marketing staff R&D
Engineering Purchasing Quality engineers Designers
Legal staff Production
Abbrev Available
MRKT 5 R&D 5 ENG 10 PURCH 2 QUAL 3 DESIGN 3 LEGAL 3 PROD 20
Hourly rate
$ 80/hr $ 80/hr $100/hr $ 60/hr $ 80/hr $ 60/hr $120/hr $ 60/hr
Include a Gantt chart with the schedule table after leveling outside of slack.
Note: No splitting of activities is allowed.
Note: No partial assignments (e.g.,50 percent). All resources mu

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!