Question: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 25 31 43 B 1
|
|
|
|
| TIMES (days) |
|
| Activity | Start Node | Finish Node | OPTIMISTIC to | MOST LIKELY tm | PESSIMISTIC tp |
| A | 1 | 2 | 25 | 31 | 43 |
| B | 1 | 3 | 20 | 26 | 44 |
| C | 2 | 5 | 10 | 22 | 34 |
| D | 3 | 4 | 27 | 39 | 51 |
| E | 4 | 5 | 11 | 32 | 53 |
Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity Ate = 32 Standard Deviation = 3 Activity Bte =
Standard Deviation =
Activity Cte =
Standard Deviation =
Activity Dte =
Standard Deviation =
Activity Ete =
Standard Deviation = 7 Path 1 2 5 Mean Time =
Standard Deviation =5 Path 1 3 4 5 Mean Time =
Standard Deviation =