Question: Question 4 options: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 24 33
Question 4 options:
|
|
|
|
| TIMES (days) |
|
| Activity | Start Node | Finish Node | OPTIMISTIC to | MOST LIKELY tm | PESSIMISTIC tp |
| A | 1 | 2 | 24 | 33 | 60 |
| B | 1 | 3 | 24 | 30 | 42 |
| C | 2 | 5 | 11 | 35 | 59 |
| D | 3 | 4 | 30 | 48 | 66 |
| E | 4 | 5 | 13 | 25 | 49 |
Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity Ate = 36 Standard Deviation = 6 Activity Bte =
Standard Deviation =
Activity Cte =
Standard Deviation =
Activity Dte =
Standard Deviation =
Activity Ete =
Standard Deviation = 6 Path 1 2 5 Mean Time =
Standard Deviation =10 Path 1 3 4 5 Mean Time =
Standard Deviation =