Question: To be valid, a Master Production Schedule needs any two of the following three items: a specific item (part number), a quantity and a due

To be valid, a Master Production Schedule needs any two of the following three items: a specific item (part number), a quantity and a due date Group of answer choices True FalseCalculate the Schedule Receipt, On Hand and Planned Order Release values for Week 8 in the MRP worksheet below: On Hand = 1,500 Lead Time = 4 weeks Lot Size = 250 Week 1 2 3 4 5 6 7 8 9 10 Gross Requirements 75 125 175 40 320 210 150 90 150 25 Schedule Receipt On Hand 1,500 Planned Order Release Group of answer choices 0, 315, 0 250, 335, 250 250. 275, 500 250, 540, 250