Question: To complete the first setup on a new machine took an employee 1 2 0 minutes. Using an 7 5 % incremental unit - time

To complete the first setup on a new machine took an employee 120 minutes. Using an 75% incremental unit - time learning model indicates that the second setup on the new machine is expected to
take
A.210 minutes
B.90 minutes
C.160 minutes
D.30 minutes