Question: This question: 1 point ( s ) possible To complete the first setup on a new machine took an employee 1 8 0 minutes. Using

This question: 1 point(s) possible
To complete the first setup on a new machine took an employee 180 minutes. Using an 90% incremental unit - time learning model indicates that the second setup on the new machine is expected to take
A.200 minutes
B.18 minutes
C.162 minutes
D.342 minutes