Question: To manage a project effectively, work should be broken down into small pieces. Which of the following statements is incorrect about decomposing the work? It

To manage a project effectively, work should be broken down into small pieces. Which of the following statements is incorrect about decomposing the work? It should be broken down:Group of answer choicesUntil it has a meaningful conclusionUntil it cannot be logically subdivided furtherUntil it can be done by one person