Question: Todd is working on resource scheduling in preparation for the start of the project. However, there are potential problems with the new collective bargaining agreement
Todd is working on resource scheduling in preparation for the start of the project. However, there are potential problems with the new collective bargaining agreement with the company's union that has not been finalized. Todd decides to purchase insurance against the risks associated with a strike. Todd's approach would best be considered an example of which method for dealing with project risk?