Question: Tom is working on a project to develop and deliver inventory management software to Canadian Hardware Inc. The critical time is 80 days. Canadian Hardware

Tom is working on a project to develop and deliver inventory management software to Canadian Hardware Inc. The critical time is 80 days. Canadian Hardware Inc. has indicated that they must have the finished product in 100 days. The Project Float is

80 days

100 days

20 days

Zero project float