Question: ______ tool allows project managers to arrange work activities graphically in sequence and analyze the flow of work throughout the project lifecycle. a.Network diagram b.RBS

______ tool allows project managers to arrange work activities graphically in sequence and analyze the flow of work throughout the project lifecycle.

a.Network diagram

b.RBS

c.WBS

d.Gantt Chart