Question: TOPIC 8 EXERCISE 1 A project consists of the activities in the following table. Times are given in weeks table [ [ Activity ,
TOPIC EXERCISE
A project consists of the activities in the following table. Times are given in weeks
tableActivityPreceding,TimeABCADA BECFD
a Draw the network diagram
b Calculate the ES EF LS LF and slack for each activity
c What is this project completion time?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock