Question: TOPIC 8 EXERCISE 1 A project consists of the activities in the following table. Times are given in weeks table [ [ Activity ,

TOPIC 8 EXERCISE
1 A project consists of the activities in the following table. Times are given in weeks
\table[[Activity,Preceding,Time],[A,,8],[B,,3],[C,A,7],[D,A, B,3],[E,C,4],[F,D,6]]
a. Draw the network diagram
b. Calculate the ES, EF, LS, LF, and slack for each activity
c. What is this project completion time?