Question: TRUE OR FALSE QUESTIONS Each question carries 1 (ONE) mark 1. A lack of readily available engineers is a technical constraint. 2. Scheduling time-constrained projects
TRUE OR FALSE QUESTIONS Each question carries 1 (ONE) mark 1. A lack of readily available engineers is a technical constraint. 2. Scheduling time-constrained projects focuses on resource utilization. 3. Managers have several effective methods for crashing specific project activities when resources are not constrained. 4. The total cost for each possible duration of a project is the sum of labor, materials, and equipment. 5. The sum of the costs of all the work packages represents the total direct costs for the project.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
