Question: Two activities on different critical paths that share no common nodes are candidates for crashing on a CPM network. Activity details are in the table
Two activities on different critical paths that share no common nodes are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, the manager should crash activity(ies) ________, adding ________ to project cost.
| Activity | Normal Time | Normal Cost | Crash Time | Crash Cost |
| B | 4 days | $6,000 | 3 days | $8,000 |
| C | 6 days | $4,000 | 4 days | $6,000 |
A) B; $2,000
B) C; $2,000
C) C; $1,000
D) B & C; $3,000
E) B & C; $4,000