Question: Two activities on different critical paths that share no common nodes are candidates for crashing on a CPM network. Activity details are in the table

Two activities on different critical paths that share no common nodes are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, the manager should crash activity(ies) ________, adding ________ to project cost.

Activity

Normal Time

Normal Cost

Crash Time

Crash Cost

B

4 days

$6,000

3 days

$8,000

C

6 days

$4,000

4 days

$6,000

A) B; $2,000

B) C; $2,000

C) C; $1,000

D) B & C; $3,000

E) B & C; $4,000