Question: Two activities on different critical paths that share no common nodes are candidates for crashing on a CPM network. Activity details are in the table

Two activities on different critical paths that

Two activities on different critical paths that share no common nodes are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, the manager should crash activity(ies) adding to project cost. A) B; $2,000 B) C; $2,000 C) C; $1,000 D) B \& C; $3,000 E) B \& C; $4,000