Question: Type or paste question here Using the information below assuming that the project team will work a standard working week (5 working days in 1

Type or paste question here

  1. Using the information below assuming that the project team will work a standard working week (5 working days in 1 week)and that all tasks will start as soon as possible:

task

description

Duration in weeks

Predecessor(s)

A

Requirement analysis

5

B

Systems design

15

A

C

programming

25

B

D

telecoms

15

B

E

Hardware installation

30

B

F

Integration

10

C,D

G

System testing

10

E,F

H

Training/support

5

G

I

Hanover and go-live

5

H

  1. Drown the project network
  2. Determine the critical path of the project using forward pass and backward pass.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!