Question: Type or paste question here Using the information below assuming that the project team will work a standard working week (5 working days in 1
Type or paste question here
- Using the information below assuming that the project team will work a standard working week (5 working days in 1 week)and that all tasks will start as soon as possible:
| task | description | Duration in weeks | Predecessor(s) |
| A | Requirement analysis | 5 | |
| B | Systems design | 15 | A |
| C | programming | 25 | B |
| D | telecoms | 15 | B |
| E | Hardware installation | 30 | B |
| F | Integration | 10 | C,D |
| G | System testing | 10 | E,F |
| H | Training/support | 5 | G |
| I | Hanover and go-live | 5 | H |
- Drown the project network
- Determine the critical path of the project using forward pass and backward pass.