Question: Dummy activities A . are used when two activities have identical starting and ending events. B . cannot be on the critical path. C .

Dummy activities
A. are used when two activities have identical starting and ending events.
B. cannot be on the critical path.
C. have a duration equal to the shortest non-dummy activity in the network.
D. are found in both AOA and AON networks.
 Dummy activities A. are used when two activities have identical starting

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!