Question: Under an option B NEC3 contract the Project Manager fails to respond to the notified compensation event. Four weeks later the Contractor realises that. What

Under an option B NEC3 contract the Project Manager fails to respond to the notified compensation event. Four weeks later the Contractor realises that. What options are available to the Contractor? If the Project Manager continues to fail to respond to a notified compensation even, what impact will this ultimately have?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!