Question: Under Normal time, if the latest finish ( LF ) time of activities F and G were 2 8 , what would be the latest

Under Normal time, if the latest finish (LF) time of activities F and G were 28, what would be the latest finish (LF) time of activity E?____
____
A)23
B)16
C)25
D)18