Question: Updated Case 6.2: Montview Stadium Case Question 2. What is the critical path for the project? List the activities on the critical path. Table 1:
Updated Case 6.2: Montview Stadium Case
Question 2. What is the critical path for the project? List the activities on the critical path.
Table 1: Montview Baseball Stadium Case
| ID | Activity | Duration (days) | Predecessor(s) |
| 1 | Clear stadium site | 75 | - |
| 2 | Demolish present stadium | 40 | 1 |
| 3 | Establish construction site | 70 | 2 |
| 4 | Drive support piling | 110 | 3 |
| 5 | Install lower bowl | 125 | 4 |
| 6 | Install main concourse | 110 | 5 |
| 7 | Install playing field | 95 | 5 |
| 8 | Construct upper steel bowl | 110 | 5 |
| 9 | Install seats | 160 | 8 |
| 10 | Build luxury boxes | 90 | 8 |
| 11 | Install Jumbotron | 25 | 8 |
| 12 | Install infrastructure | 110 | 8 |
| 13 | Build steel canopy | 80 | 9 |
| 14 | Install lighting | 25 | 9 |
| 15 | Construct roof supports | 90 | 3 |
| 16 | Build roof | 150 | 15 |
| 17 | Construct roof racks | 90 | 13 |
| 18 | Install roof supports | 90 | 16,17 |
| 19 | Final inspection | 25 | 7,10,12,14,18 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
