Question: Updated Case 6.2: Montview Stadium Case Question 2. What is the critical path for the project? List the activities on the critical path. Table 1:

Updated Case 6.2: Montview Stadium Case

Question 2. What is the critical path for the project? List the activities on the critical path.

Table 1: Montview Baseball Stadium Case

ID

Activity

Duration (days)

Predecessor(s)

1

Clear stadium site

75

-

2

Demolish present stadium

40

1

3

Establish construction site

70

2

4

Drive support piling

110

3

5

Install lower bowl

125

4

6

Install main concourse

110

5

7

Install playing field

95

5

8

Construct upper steel bowl

110

5

9

Install seats

160

8

10

Build luxury boxes

90

8

11

Install Jumbotron

25

8

12

Install infrastructure

110

8

13

Build steel canopy

80

9

14

Install lighting

25

9

15

Construct roof supports

90

3

16

Build roof

150

15

17

Construct roof racks

90

13

18

Install roof supports

90

16,17

19

Final inspection

25

7,10,12,14,18

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!