Question: URGENT: Kindly answer the question i will rate your answer asap. The pointed lead company manufactures designer pencils. Their on hand inventory at the end

URGENT: Kindly answer the question i will rate your answer asap.

The pointed lead company manufactures designer pencils. Their on hand inventory at the end of the Week (week 3) was 45 and they are expecting an inventory order of 100 to come in tonight before the start of the new week (Week 4). Their projected requirements this week are 115. What is their projected on hand inventory at the end of this week (Week 4)?