Question: Use excel to solve. General Foundrys project crashing data are shown below. Crash this project to 13 weeks using CPM. What is the final time
Use excel to solve.
General Foundrys project crashing data are shown below. Crash this project to 13 weeks using CPM. What is the final time for each activity after crashing? What is the crash cost per week per activity and the total cost of crashing?
|
| TIME (WEEKS) | COST ($) | |||
| ACTIVITY | IMMEDIATE PREDECESSORS | NORMAL | CRASH | NORMAL | CRASH |
| A | 2 | 1 | 22,000 | 23,000 | |
| B | 3 | 1 | 30,000 | 34,000 | |
| C | A | 2 | 1 | 26,000 | 27,000 |
| D | B | 3 | 2 | 48,000 | 49,000 |
| E | C | 4 | 2 | 56,000 | 58,000 |
| F | C | 3 | 2 | 30,000 | 30,500 |
| G | D, E | 5 | 2 | 80,000 | 83,000 |
| H | F, G | 2 | 1 | 16,000 | 19,000 |