Question: Use expected finish time to decide ES, EF, LS, LF of each activity. What is the LF time of activity C? What is the slack

Use expected finish time to decide ES, EF, LS, LF

  1. Use expected finish time to decide ES, EF, LS, LF of each activity. What is the LF time of activity C? What is the slack time of activity F?
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm A None 4 5 6 B None 2 4. 6 1 4 7 . D A 2 5 8 E C, D 3 9 27 F 3 6 15 G E, F 3 6 21 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as 4.32