Question: Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (Machine 1


  Use Johnson's rule to determine the optimal sequencing for the five jobs 

Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (Machine 1 before Machine 2). The processing times are given in the table below. Job Machine 1 Machine 2 8 7 9 6 3 9 8 4 5 What is the total flow time of the optimal sequence? LMNOP 31 35 39 40 41 7

Step by Step Solution

3.42 Rating (149 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Optimal sequence according to johnsons rule Least number first if its left sid... View full answer